Minutes:

Paul Blunt, Traffic & Highways Works Manager presented this report to the committee.  Russell Troup, Project Engineer, was also in attendance to answer questions.  The report sought the committee’s approval to progress the Beddington Lane Regeneration scheme, so that a formal application for funding could be made to Transport for London (TfL) to implement the scheme subject to consultation and land acquisition. 

 

The scheme aimed to enhance pedestrian and cycle link facilities, encourage better use of existing bus and tram services, and improve access to the industrial units within the estate.

 

It was explained that TfL were funding this scheme in sections of which there were five sections for the whole scheme. 

 

Resolved: (i) To approve the regeneration scheme, in principal, as shown on the drawing T12001-001attached to the report.

 

(ii) To note that the consultation with stakeholders, affected parties and residents is progressing.

 

(iii) To note that approval to acquire land required for the scheme will be sought, from The Executive, subject to consultation and funding.

 

(iv) To approve implementation of the scheme in stages as funding becomes available, subject to consultation and land acquisition.

 

(v) To delegate authority to the Executive Head of Planning, Transport and Highways in consultation with the Chair, Ward Councillors and Lead Councillor, to agree and if necessary, modify details to address any further issues that may arise from ongoing consultations of the above scheme.

 

(vi) To thank Russell Troup for the work he had done on this.