7 Release of Capital Funding for Highways Maintenance Programme 2015/16 and update on procurement of highways and lighting contracts pdf icon PDF 88 KB

The Planned Carriageway and Footway Maintenance Works Programme is drawn up to address the more important maintenance requirements of roads in the Borough through a prioritisation process and this report seeks approval to incur capital expenditure for the roll out of the programme in 2015/16. The report also updates on progress regarding the re-procurement of the highways and street lighting contracts and the basis of the agreed extension of these existing contracts, as agreed at the January Environment and Neighbourhoods Committee.

Additional documents:

Minutes:

The Committee considered a report on the Planned Carriageway and Footway Maintenance Works Programme and a progress update on the re-procurement of the highways and street lighting contracts. 

 

An error was highlighted in Appendix A to the report (roads to be resurfaced) where the ward for Woodside Road should just read Sutton North.  Officers also confirmed that Christmas lights were not included in this programme but came under Local Committees Public Realm funding.

 

Resolved:

1.    To incur capital expenditure for the 2015/16 Planned Carriageway and Footway Maintenance Programmes as outlined in the 2012-2016 Capital Programme.